§ 16.16.470. Change in contractor—Reissuance of permit—Fees.
Latest version.
When a change in a contractor occurs before a job is completed, the gas/mechanical contractor who obtains the permits, shall notify the gas/mechanical official in writing. A new permit shall be taken out for the unfinished construction. The gas/mechanical contractor that completes the construction shall pay a prorata permit fee based upon the unfinished construction; but in no case, less than the minimum permit fee.
(Ord. 90-1253 § 1 (part), 1990; prior code § 19-1-67.1)