§ 16.16.520. Time schedule.  


Latest version.
  • Upon notification from the certificate holder or gas/mechanical contractor, codes administration gas/mechanical inspectors shall make the following inspections of gas/mechanical systems:

    A.

    Rough Piping Inspection. The rough piping inspection is to be made after trenches or ditches are excavated and all new fuel piping authorized by the permit has been installed, and before any such piping has been backfilled or covered or concealed or any fixtures or gas appliances have been connected.

    B.

    Final Piping Inspection. The final piping inspection is to be made after all gas piping authorized by the permit has been installed and after all portions have been concealed and before any fixtures or gas appliances have been connected. This inspection shall include a pressure test.

    C.

    Rough-In Inspection. The rough-in inspection is to be made after the roof, framing, draftstopping, fire-blocking and bracing are in place, all ducting and other concealed components are complete and in place and prior to the installation of wall or ceiling membranes.

    D.

    Final Inspection. The final inspection is to be made after building is complete, the gas/mechanical systems are in place and properly connected, and the structure is ready for occupancy.

(Ord. 90-1253 § 1 (part), 1990; prior code § 19-1-75)