§ 16.16.540. Retesting and reinspection—Fee.  


Latest version.
  • When the gas or mechanical installation does not pass the required inspections, the permittee shall be required to make the necessary changes and corrections and to submit the gas or mechanical installation to reinspection within ten working days after rejection. In all instances where reinspections are deemed necessary, an additional fee of twenty-five dollars shall be paid for each reinspection required.

(Ord. 90-1253 § 1 (part), 1990; prior code § 19-1-78)