§ 16.28.210. Work authorized—Plumbing and electrical permit requirements applicable.  


Latest version.
  • A.

    A general building permit shall carry with it the right to install in any new building or structure or part thereof any heating system, air conditioning or ventilating system or unit, storm drains not connected to a public sanitary sewer system, elevators, sidewalk elevators, vaults, chutes, coal holes, lifts, cranes, derricks, steam power boilers, steam, oil, gas or vapor engines or similar equipment or devices, and the right to treat any building or structure for termites or termite protection, provided such equipment, devices or treatments are incorporated into the plans and set forth in the specifications submitted with the application for a building permit. Where such equipment and devices or treatments are not incorporated into the plans and specifications submitted with the application for a building permit, a separate building permit shall be required. Where structural damage caused by termites is required to be replaced, the building permit fees as set forth in Section 16.28.110 shall be paid.

    B.

    The issuance of a building permit shall not be construed as waiving the requirement for a plumbing or electrical permit for the installation of any plumbing or electrical system, device or equipment necessary or required for proper operation of such installations.

(Prior code § 11-1-51)