    Upon completion of a building erected in accordance with approved plans, and after the final inspection and upon application therefor, the department of codes administration shall issue a certificate of occupancy stating the nature of the occupancy permitted, the number of persons for each floor when limited by law and the allowable load per square foot for each floor in accordance with the provisions of Sections 2.80.010 through 2.80.110 and Chapters 16.04, 16.08, 16.28 and 16.36 through 16.56.

    B.

    The metropolitan department of codes administration shall have three days from the time they are notified to inspect a building or dwelling for a use and occupancy permit. If a violation is found, the permit shall be withheld. If the inspection is not made within three working days, the permit shall be deemed to be granted and the permit shall be issued by the department.

(Prior code § 11-1-60)