§ 6.26.080. Adjustment of utility facilities.  


Latest version.
  • In the event that the location of grantee's system will require an adjustment of the installation of existing public or private utility facilities, grantee must obtain written consent of the owner of such utility, including, where applicable, all relevant metropolitan government departments to such adjustment and make such arrangements for the payment or reimbursement of the cost of such adjustment as are satisfactory to the owner of such utility, including, where applicable, all relevant metropolitan government departments. No permit for construction will be issued until the director of the department of public works is satisfied that the requirements of this section have been satisfied. In no case shall grantee be entitled to perform such adjustment or disturb such utility facilities without the written consent of the owner of such utility.

(Amdt. 1(10) to Ord. 94-1103, 7/19/94; Ord. 94/1103 § 8, 1994)